Feature Request: Work Breakdown Structure

I'd like to produce a WBS in conjunction with my requirements. My WBS items would map to individual requirements, but I would need to add additional data to each requirement record. This addl data is needed to help further define the WBS items' functional areas. So basically the WBS would be a report, and including this capability would keep these two documents in synch.

So for starters, does this resonate with anyone? How does the existing architecture of Contour support (or not) this idea?

Thank you,

Andy

Click to view Eric's profile   82 posts since
Jun 11, 2007
1. Apr 4, 2008 12:07 AM in response to: ajohnson@dukesinc.com
Re: Feature Request: Work Breakdown Structure
Hi Andy,

That does resonate, and we often discuss where to draw the line with regards to WBS, scheduling etc in Contour. Tell me a little more about what you're trying to accomplish with regard to output... is this to tie to another system, or would you see sub tasks as part of this structure within Contour, reporting etc?

Or are you just thinking of categorizing requirements by their WBS structure - a simple option would be to add additional fields to track this, then develop a report that groups by this data.

We are also discussing / planning for a connection with Microsoft Project that may offer some solution to what you are after... MS Project

If you want to discuss more in detail, give us a call and we and talk it through.